Dear fellow engineers,
In a refugee camp reconstruction, we have the following dilemma:
First, we have an existing retaining wall, height up to 4.5 meters, thickness ranging from 0.25 to 0.4 m. On the back of the wall we have existing an layer of cyclopean concrete :height up to 4.5, width 3m, and length along the wall.
A 5 story building is to be built over the cyclopean concrete. This means that the Raft of the building (0.5m thick) will lie directly above the existing wall.
The question is, what is the calculation required to ensure that this wall will withstand the loads of the raft?